TAMIL NADU
GENERATION AND DISTRIBUTION
CORPORATION LIMITED
(ABSTRACT)
Allowance
– Gas Turbine Schemes – Revision of Special (Gas Turbine Schemes) Allowance to
the employees/ officers working in Thirumakottai, Kuttalam and Valuthur Gas Turbine Power Stations - Orders –Issued.
------------------------------------------------------------------------------------------
(SECRETARIAT
BRANCH)
(Per)
FB TANGEDCO Proceedings No.22,
Dated : 25-7-2015.
Aadi -9,
Thiruvalluvar Aandu 2046.
Read:-
1)
(Per) B.P. (Ch) No.112, (SB) dt. 10.5.2007.
2) (Per) B.P. (Ch)
No.108, (SB) dt. 20.6.2008.
3)
(Per) B.P. (Ch) No.223 (SB) dt.21-11-2009.
4) (Per) B.P. (Ch) No.224 (SB)
dt.21-11-2009.
5) Minutes of the 57th
Board Meeting of TANGEDCO
held on
17.7.2015.
------
Proceedings:-
In the Board’s Proceedings first cited,
orders have been issued for payment of Special (Gas Turbine Schemes) Allowance
at flat rate basis to the employees/officers of Thirumakkottai (K) Gas Turbine
Power Station.
2) Subsequently, in the Board’s
Proceedings second cited, orders have been issued for payment of Special (Gas
Turbine Schemes) Allowance at flat rate basis to the employees/officers of
Valuthur Gas Turbine Power Station and Kuttalam Gas Turbine Power Station .
3) The Chief Engineer/Gas Turbine
Schemes/Chennai had sent a proposal for revision of Special (Gas Turbine Schemes) Allowance to the
employees/officers of the Valuthur Gas Turbine Power Station, Kuttalam Gas
Turbine Power Station and Thirumakkottai (K) Gas Turbine Power Station, stating
that the above stations
are located in remote places, where there is no residential quarters and
thereby much difficulties are caused to the Operation and Maintenance Personnel
to reach the station, in case of emergency during night hours due to lack of transport
facilities. The proposal was examined in
detail.
.. 2 ..
:: 2 ::
4)
At the time of Revision of wages ordered with effect from 1-12-2007, the Revision of
Allowances/Special Pay was given effect to from 1-9-2009 to the employees /
Officers as in the reference third and fourth cited, the
Special Gas Allowance has not been revised since it was newly
implemented to the Gas Stations during 2007-08 only.
5) After careful consideration, the TANGEDCO hereby
orders that the existing Special (Gas Turbine Schemes) Allowance be doubled
at the flat rate as in the Annexure to the employees/ officers of the Valuthur Gas Turbine Power Station, Kuttalam
Gas Turbine Power Station and Thirumakkottai (K) Gas Turbine Power Station .
6) The payment of Special (Gas Turbine Schemes)
Allowance ordered in para-5 above shall take effect from the date of issue of this order.
7)
The expenditure sanctioned in para-3 above is debitable to “Tamil Nadu
Electricity Board Funds” – Revenue Expenses – 75.410 Employees cost – Other Allowance - Special
(Gas Turbine Schemes) Allowance.
8) The receipt of the Board’s Proceedings
shall be acknowledged.
(BY ORDER OF THE BOARD)
R. KRISHNAN
SECRETARY (ADDL. CHARGE).
To
The Chief Engineer/Gas Turbine Schemes.
The Chief
Engineer/Personnel/Administrative Branch/Chennai-2.
The Chief
Financial Controller/General & Revenue/Chennai.
The Superintending
Engineer/Thirumakkottai (K) Gas Turbine Power Station.
The Superintending
Engineer /Valuthur Gas Turbine Power Station .
The Superintending
Engineer /Kuttalam Gas Turbine Power Station
.
The Superintending
Engineer /Gas Turbine Power Station /Chennai.
The
Chief Internal Audit Officer/Audit Branch/Chennai -2.
The
Residential Audit Officer /Chennai -2.
Copy
to:-
The
Chairman cum Managing Director's Table.
The
Director General of Police/Vigilance.
The
Managing Director/TANTRANSCO.
All
Directors/TANGEDCO and TANTRANSCO.
The
Secretary / TANGEDCO / Chennai-2.
.. 3 ..
:: 3 ::
The
Legal Adviser.
The Executive Assistant to Chairman cum
Managing Director’s office.
The
Industrial Relations Adviser/TANGEDCO.
The
Deputy Chief Engineer/Administrative Branch.
All
Senior Personnel Officers/Administrative Branch.
The
Industrial Relations Officer/TANGEDCO.
The
Assistant Personnel Officer/Tamil Development – for Publication
in the TNEB Bulletin (2 copies).
All
Branches.
Tamil
Nadu Electricity Workers' Federation.
Tamil
Nadu Electricity Board Accounts & Executive
Staff Union .
Tamil
Nadu Electricity Board Workers Progressive Union (LPF).
Central
Organisation of Tamil Nadu Electricity Employees (COTEE).
Minsara
Pirivu Anna Thozhir Sangam.
Tamil
Nadu Minvariya Janatha Thozhilalar Sangam.
Tamil
Nadu National Electricity Workers' Federation (2 Groups).
Tamil
Nadu Electricity Board Engineers' Sangam.
Tamil
Nadu Electricity Employees Congress.
Tamil
Nadu Electricity Board Thozhilalar Aykkiya Sangam.
Tamil
Nadu Electricity Board Engineers' Association.
Tamil
Nadu Electricity Board Finance & Accounts Officers Association.
Bharathiya
Electricity Employees Federation.
Tamil
Nadu Electricity Board Card Billing Staff Union.
Tamil
Nadu Electricity Board Dr.Ambedkar Employees Union.
Tamil
Nadu Electricity Board Engineers Union .
:: TRUE COPY :: FORWARDED :: BY ORDER
::
SECTION OFFICER.
p.t.o. for Annexure.
ANNEXURE
SPECIAL (GAS TURBINE SCHEMES) ALLOWANCE
Existing
Pay Range
(Rs.)
|
Revised Pay Range
(Pay + GP)
(Proposed)
(Rs.)
|
Existing
Special (G.T.S.) Allowance
(Rs.)
|
Revised
Special
(G.T.S)
Allowance (Doubled)
(Rs.)
|
||||||||
Upto 3,500
3,501-4,000
4,001-4,500
4,501-5,000
5,001-5,500
5,501-6,000
6,001-7,000
7,001-8,000
8,001-9,000
9,001-10,000
10,001-11,000
11,001-12,000
12,001-13,000
13,001 and above
|
Upto 7649
7650-9399
9400-10699
10700-11999
12000-13299
13300-14599
14600-15899
15900-17399
17400-19199
19200-21699
21700-25599
25600-29799
29800 -34000
34000 and above
|
320
370
420
470
520
580
640
740
840
940
1,040
1,150
1,260
1,370
|
640
740
840
940
1,040
1,160
1,280
1,480
1,680
1,880
2080
2300
2520
2740
|
||||||||
NOTE: In cases where the revised rate of
Allowance falls short of double the rate in the existing
|
|||||||||||
|
quantum of Allowance due to revised Pay
Ranges, in such cases the quantum of Allowance
|
||||||||||
|
shall be actually doubled.
|
|
|
|
|
||||||
//
TRUE COPY //